Oracle sends force majeure notice for Stargate data center in New Mexico

Oracle sent a force majeure notice to the developer of Project Jupiter, a Stargate data center campus in New Mexico, TechCrunch reported, citing Bloomberg. The notice would allow Oracle to delay payments if the facility misses its target to come online in 2028. Bloomberg’s sources said the company is not seeking to leave as the campus’s main tenant. Oracle told CNBC that the project remains on schedule and that it remains committed to New Mexico; Blue Owl Capital, whose unit received the notice, said it does not change the project’s financial commitments.

The 2.45-gigawatt campus faces obstacles related to its energy supply. An Energy Transfer gas pipeline has been delayed by nearly six months, to February 1, 2027, while permits remain an issue, and an air-quality permit for Bloom Energy fuel cells is still pending. The project also faces opposition from residents and environmental groups.

Why it matters · editorial interpretation

The force majeure notice highlights how delays involving gas supply, permits and local opposition could affect the financial commitments and schedule of a 2.45-gigawatt campus. Oracle says the project remains on schedule and that it remains committed to New Mexico, while Blue Owl says the financial commitments are unchanged.

Sources

BusinessHardware

One story, many sources

Coverage of the same story gathered in one item, with a link to each original.

Summary and interpretation apart

What the sources say stays in the summary; editorial context is labeled separately.

Made with AI, with sources

Summaries and translations generated with AI from the original stories, always linked.